StreakPeaked· Practice

ExamsSSC CGL (Prelims)General › Time and Work

SSC CGL (Prelims) General: Time and Work questions with solutions

43 questions with worked solutions.

Questions

Q1. P and Q together can complete a job in 16 days. Q and R together can complete it in 24 days, and R and P together can do it in 32 days. In how many days can P alone complete the job?

  1. 30 1/2 days
  2. 32 days
  3. 38 2/5 days
  4. 48 days

Answer: 38 2/5 days

Let daily work rates be P, Q, and R. Then \(P+Q=1/16\), \(Q+R=1/24\), and \(R+P=1/32\). Adding gives \(2(P+Q+R)=1/16+1/24+1/32=13/96\), so \(P+Q+R=13/192\). Hence \(P=(P+Q+R)-(Q+R)=13/192-1/24=5/192\), so P alone takes \(192/5=38\frac{2}{5}\) days.

Q2. X can complete a project in 14 days and Y in 10 days. When Z joins them, the work is finished in 3.5 days. How many days would Z need alone?

  1. 8 days
  2. 8.75 days
  3. 9.33 days
  4. 10 days

Answer: 8.75 days

X’s rate is $1/14$ per day and Y’s rate is $1/10$ per day. Together with Z, the rate is $1/3.5=2/7$ per day. So Z’s rate is $2/7 - 1/14 - 1/10 = 2/35$, meaning Z alone takes 35/4 = 8.75 days.

Q3. P can complete a task in 6 days, and Q can destroy it in 4 days. P works for 3 days, then Q joins for 2 days. In how many days will P finish the remaining work alone?

  1. 6 days
  2. 7.5 days
  3. 4 days
  4. 9 days

Answer: 4 days

P’s rate is $1/6$ per day and Q’s rate is $-1/4$ per day. In 3 days P completes $1/2$ work; in the next 2 days, together they do $2(1/6-1/4)=-1/6$ work, so remaining work is $1/2+1/6=2/3$. P alone needs $(2/3)/(1/6)=4$ days.

Q4. A traveller goes from City P to Q at 24 km/h in 5 hours. By how much should the speed be increased to complete the journey in 3 hours?

  1. 16 km/h
  2. 20 km/h
  3. 24 km/h
  4. 28 km/h

Answer: 16 km/h

The distance between the cities is $24 \times 5 = 120$ km. To cover 120 km in 3 hours, the required speed is $120/3 = 40$ km/h. So the increase in speed is $40 - 24 = 16$ km/h.

Q5. X can do a job in 10 days, and Y can do it in 15 days. They work together for 4 days. What fraction of the work remains?

  1. 1/6
  2. 1/5
  3. 1/4
  4. 1/3

Answer: 1/3

X's one-day work is $1/10$ and Y's one-day work is $1/15$. Together they do $1/10 + 1/15 = 1/6$ of the work per day, so in 4 days they complete $4/6 = 2/3$ of the work. Therefore, the remaining work is $1 - 2/3 = 1/3$.

Q6. X and Y complete a task in 14 days, and Y and Z complete it in 18 days. If X works for 6 days, Y for 8 days, and Z for 12 days to complete the task, how many days will Z alone take approximately?

  1. 20 days
  2. 22 days
  3. 28 days
  4. 30 days

Answer: 22 days

Let the daily work rates be X, Y, Z. Then X+Y = 1/14 and Y+Z = 1/18. The total work done is 6X + 8Y + 12Z = 1. Solving these equations gives Z ≈ 1/22 of the work per day, so Z alone takes about 22 days.

Q7. P completes a job in 15 days and Q in 20 days. P and Q agree to do the work for ₹6,000. With R, they finish in 4 days. What is R's payment?

  1. ₹ 1,800
  2. ₹ 3,200
  3. ₹ 2,400
  4. ₹ 2,800

Answer: ₹ 3,200

P's rate is $1/15$ and Q's rate is $1/20$, so together they work at $7/60$ per day. In 4 days, P+Q do $28/60=7/15$ of the work, so R does the remaining $8/15$. Therefore R's payment is $6000\times \frac{8}{15}=3200$.

Q8. The ratio of the times taken by X and Y to complete a task is $5:3$. If Y alone takes 15 hours, how long will X and Y together take?

  1. 8.5 hrs
  2. 9.375 hrs
  3. 10 hrs
  4. 11 hrs

Answer: 9.375 hrs

Since time is inversely proportional to work rate, X:Y time ratio $=5:3$ means X:Y efficiency ratio $=3:5$. If Y takes 15 hours, X takes $15\times \frac{5}{3}=25$ hours. Together their rate is $1/25+1/15=8/75$, so time taken is $75/8=9.375$ hours.

Q9. C is four times as efficient a worker as D, and C can complete a work in 45 days less than D. If they work together, in how many days can they finish the work?

  1. 10 days
  2. 12 days
  3. 15 days
  4. 18 days

Answer: 12 days

If D takes x days, then C, being four times as efficient, takes x/4 days. Given x - x/4 = 45, so x = 60 and C takes 15 days. Together, their rate is 1/15 + 1/60 = 1/12, so they finish in 12 days.

Q10. P and Q can complete a work in 16 days and 24 days, respectively. They begin the work together, but Q leaves after 6 days. How many more days will P take to finish the remaining work?

  1. 7 1/4 days
  2. 8 1/2 days
  3. 6 days
  4. 10 1/3 days

Answer: 6 days

P’s rate is 1/16 per day and Q’s rate is 1/24 per day, so together they do 5/48 of the work per day. In 6 days they complete 5/8 of the work, leaving 3/8, which P finishes in 6 days.

Q11. M and N can complete a certain project together in 36 days. After M works for 20 days, N is left to finish the remaining work by himself in 52 days. How many days would it take N to complete the entire project on his own?

  1. 78 days
  2. 84 days
  3. 72 days
  4. 96 days

Answer: 72 days

Let M’s and N’s daily work rates be \(m\) and \(n\). Then \(m+n=1/36\). Also, after M works for 20 days, the remaining work is what N completes in 52 days, so \(1-20m=52n\). Solving these two equations gives \(n=1/72\), so N alone takes 72 days.

Q12. P, Q, and R can complete a certain work in 24, 36, and 72 days, respectively. How many days will it take for P to finish the work if he receives help from Q and R every fourth day?

  1. 16 days
  2. 17 days
  3. 18 days
  4. 19 days

Answer: 19 days

P’s 1-day work = \(1/24\), Q’s = \(1/36\), and R’s = \(1/72\). In every 4-day cycle, P works 4 days and gets help from Q and R on the 4th day, so total work per cycle is \(3\cdot\frac{1}{24}+\left(\frac{1}{24}+\frac{1}{36}+\frac{1}{72}\right)=\frac{1}{8}+\frac{1}{12}=\frac{5}{24}\). After 4 such cycles, 20 days, the work would exceed 1, so the exact completion occurs on day 19.

Q13. Pipe A can fill a tank in 18 minutes and Pipe B can fill it in 36 minutes. Both are opened together. After 6 minutes, the rate of Pipe A becomes half and Pipe B’s rate becomes double. How many more minutes are required to fill the tank?

  1. 5 min
  2. 6 min
  3. 7 min
  4. 8 min

Answer: 6 min

Initially, A fills $1/18$ tank per minute and B fills $1/36$ per minute, so together they fill $1/12$ tank per minute. In 6 minutes they fill $6/12 = 1/2$ tank. After the change, A works at $1/36$ and B at $1/18$, so the combined rate is again $1/12$ tank per minute; thus the remaining half takes 6 more minutes.

Q14. Tap X and Tap Y can fill a cistern in 12 hours and 15 hours respectively. An outlet pipe Z can empty it in 20 hours. If all three are opened together, how long will it take to fill the empty cistern?

  1. 8 hours
  2. 12 hours
  3. 10 hours
  4. 15 hours

Answer: 10 hours

Tap X fills \(\frac{1}{12}\) cistern per hour and Tap Y fills \(\frac{1}{15}\) per hour, while Z empties \(\frac{1}{20}\) per hour. Net rate = \(\frac{1}{12}+\frac{1}{15}-\frac{1}{20}=\frac{1}{10}\) cistern per hour, so the cistern fills in 10 hours.

Q15. Two pipes A and B can fill a tank in 10 and 15 minutes respectively. After both are opened together for 3 minutes, the rate of pipe A becomes one-third, and pipe B becomes 2.5 times its original rate. In how many more minutes will the tank be full?

  1. 2 min 15 sec
  2. 3 min 10 sec
  3. 2 min 30 sec
  4. 1 min 45 sec

Answer: 2 min 30 sec

Initially, A fills \(1/10\) tank/min and B fills \(1/15\) tank/min, so together they fill \(1/6\) tank/min. In 3 minutes, they fill \(1/2\) tank. After that, A’s rate becomes \(\frac{1}{3}\cdot\frac{1}{10}=\frac{1}{30}\) and B’s rate becomes \(2.5\cdot\frac{1}{15}=\frac{1}{6}\), so combined rate is \(\frac{1}{5}\) tank/min. Remaining half tank takes \(\frac{1/2}{1/5}=2.5\) minutes = 2 min 30 sec.

Q16. P and Q are hired for a project for ₹1200. P starts the work alone; Q joins when 20% of the work is completed. If Q is 1.5 times as efficient as P, calculate Q's total earnings.

  1. ₹ 500
  2. ₹ 600
  3. ₹ 720
  4. ₹ 576

Answer: ₹ 576

Let P's efficiency be 1 unit and Q's efficiency be 1.5 units. P does 20% of the work alone, and the remaining 80% is done together in the ratio 1 : 1.5 = 2 : 3. So Q's share of the total work is \(\frac{3}{5}\times 80\% = 48\%\), hence Q earns \(48\%\) of ₹1200 = ₹576.

Q17. A and B together earn ₹1200 for a job. A works the whole time; B joins after 40% of the job is done. B is 1.5 times as efficient as A. Find B's share.

  1. ₹432
  2. ₹768
  3. ₹500
  4. ₹600

Answer: ₹432

Let A's efficiency be 1 and B's be 1.5. If the total job is 1 unit, A does all of it, while B does only the last 60%, so B's work contribution is $1.5\times 0.6=0.9$ units and A's is 1 unit. Thus the ratio A:B is $1:0.9=10:9$, so B's share is $1200\times\frac{9}{19}=₹432$.

Q18. A boy and a girl are together filling a tank with water. The boy pours 5 liters every 4 minutes, while the girl pours 4 liters every 5 minutes. How much time will it take to fill 82 liters of water in the tank?

  1. 35 min
  2. 50 min
  3. 45 min
  4. 40 min

Answer: 40 min

The boy's rate is \(5/4\) L/min and the girl's rate is \(4/5\) L/min. Their combined rate is \(5/4+4/5=41/20\) L/min. Time to fill 82 liters is \(82\div(41/20)=40\) minutes.

Q19. If 4 workers take 4 days to build 4 walls, how long will 50 workers take to build 50 walls?

  1. 4 days
  2. 50 days
  3. 25 days
  4. 10 days

Answer: 4 days

If 4 workers build 4 walls in 4 days, then 1 worker builds 1 wall in 4 days. Therefore, 50 workers will build 50 walls in the same 4 days.

Q20. P can do a piece of work in 5 days, and Q can do it in 10 days. If they work together for 2 days, how much of the work will be left?

  1. 20%
  2. 30%
  3. 40%
  4. 50%

Answer: 40%

P’s one-day work = \(1/5\), Q’s one-day work = \(1/10\). Together they do \(1/5 + 1/10 = 3/10\) of the work per day, so in 2 days they complete \(6/10 = 60\%\). Hence, 40% work is left.

Q21. 15 women can do a work in 20 days. 12 men can complete the same work in 10 days. What is the ratio between the efficiency of a man and a woman?

  1. 3:2
  2. 5:2
  3. 4:3
  4. 5:3

Answer: 5:2

15 women finish the work in 20 days, so 1 woman's 1-day work is 1/(15×20). Similarly, 12 men finish it in 10 days, so 1 man's 1-day work is 1/(12×10). The ratio of efficiency of a man to a woman is therefore [1/120] : [1/300] = 300:120 = 5:2.

Q22. X and Y can complete a task in 15 days together. X is 50% more efficient than Y. What percentage of the work is done by X alone?

  1. 50%
  2. 55%
  3. 60%
  4. 65%

Answer: 60%

If Y's efficiency is 2 units, then X's efficiency is 3 units because X is 50% more efficient. So together they work in the ratio 3:2, and X's share of the work is 3/(3+2) = 3/5 = 60%.

Q23. A group of 4 men or 6 women can complete a task in 40 days. Find the time taken by 4 men and 6 women together to complete the task.

  1. 15 Days
  2. 20 Days
  3. 24 Days
  4. 30 Days

Answer: 20 Days

Since 4 men alone finish in 40 days, their rate is \(1/40\) task per day. Similarly, 6 women alone also have rate \(1/40\) per day, so together their rate is \(1/20\) task per day, meaning 20 days.

Q24. 40 men can do a piece of work in 10 days. Find the time required by 25 men to do double the work.

  1. 28 Days
  2. 30 Days
  3. 32 Days
  4. 36 Days

Answer: 32 Days

40 men working for 10 days complete one job, so total work = 400 man-days. Double the work = 800 man-days. With 25 men, time required = \(800/25 = 32\) days.

Q25. A can do a certain work in the same time in which B and C together can do it. If A and B together can do it in 12 days and C alone can do it in 60 days, then B alone can do it in:

  1. 20 days
  2. 24 days
  3. 30 days
  4. 40 days

Answer: 30 days

Let the daily work rates of A, B, and C be a, b, and c. Given a = b + c, a + b = 1/12, and c = 1/60. Substituting a = b + c gives 2b + c = 1/12, so 2b + 1/60 = 1/12, which yields b = 1/30.

Q26. 25 workers can do a piece of work in 40 days. Find the percentage of work done by 50 workers in 5 days.

  1. 20%
  2. 30%
  3. 25%
  4. 40%

Answer: 25%

Total work = 25 × 40 = 1000 worker-days. Work done by 50 workers in 5 days = 50 × 5 = 250 worker-days. So the fraction completed is 250/1000 = 1/4 = 25%.

Q27. If 12 men can build a wall in 15 days, in how many days can 18 men complete the same work?

  1. 8
  2. 12
  3. 14
  4. 10

Answer: 10

Total work = 12 × 15 = 180 man-days. If 18 men work on it, days required = 180/18 = 10 days. So the correct answer is 10.

Q28. If 10 men or 15 women can complete a work in 170 days, how long will 20 men and 20 women take to complete the same work?

  1. 52 days
  2. 50 days
  3. 51 days
  4. 53 days

Answer: 51 days

If 10 men finish the work in 170 days, then 1 man’s 1-day work is \(\frac{1}{10\times170}\). Similarly, 1 woman’s 1-day work is \(\frac{1}{15\times170}\). Adding the rates of 20 men and 20 women gives the total daily work, from which the time comes out to 51 days.

Q29. Two taps can fill a tub in 6 minutes and 4 minutes, respectively. A pipe can empty it in 3 minutes. If all three are kept open simultaneously, when will the tub be full?

  1. 10 min
  2. 12 min
  3. 7 min
  4. 15 min

Answer: 12 min

The two taps fill at rates of \(1/6\) and \(1/4\) tub per minute, while the pipe empties at \(1/3\) tub per minute. Net rate = \(1/6 + 1/4 - 1/3 = 1/12\) tub per minute. So the tub will be full in 12 minutes.

Q30. Sudarshan can copy 50 pages in 10 hours. Sudarshan and Prakash together can copy 300 pages in 40 hours. In how much time can Prakash copy 25 pages?

  1. 10 hours
  2. 12 hours
  3. 15 hours
  4. 8 hours

Answer: 10 hours

Sudarshan’s rate is 50/10 = 5 pages per hour. Together they copy 300/40 = 7.5 pages per hour, so Prakash’s rate is 2.5 pages per hour. To copy 25 pages, Prakash needs 25/2.5 = 10 hours.

Q31. The time taken to cover 132 km by car is 1 hour. Find the time taken to cover 88 km by car.

  1. 45 min
  2. 38 min
  3. 42 min
  4. 40 min

Answer: 40 min

If 132 km takes 1 hour, then speed is 132 km/h. Time for 88 km is $88/132 = 2/3$ hour, which is 40 minutes.

Q32. A can complete a task in 15 days, and B can complete the same task in 20 days. How long will it take them to complete the task together?

  1. 5.5 days
  2. 6.5 days
  3. 7.5 days
  4. 8.5 days

Answer: 8.5 days

A’s rate is \(1/15\) work/day and B’s rate is \(1/20\) work/day. Together, their rate is \(1/15+1/20=7/60\) work/day, so time taken is \(60/7\approx 8.57\) days.

Q33. Suman and Sujata travel the same distance at speeds of 10 km/h and 12 km/h respectively. If Suman takes 36 minutes more than Sujata, the distance traveled by each is:

  1. 42 km
  2. 45 km
  3. 40 km
  4. 36 km

Answer: 36 km

The difference in times is 36 minutes = 0.6 hour. For the same distance \(d\), the time difference is \(\frac{d}{10}-\frac{d}{12}\). Solving gives \(d\left(\frac{1}{60}\right)=0.6\), so \(d=36\) km.

Q34. A car traveling at a speed of 50 km/h can complete a journey in 8 hours. How long will it take to travel the same distance at 40 km/h?

  1. 15 h
  2. 9 h
  3. 10 h
  4. 12 h

Answer: 10 h

The distance covered is 50 × 8 = 400 km. At 40 km/h, time taken = 400/40 = 10 hours. So the correct answer is 10 h.

Q35. The efficiency of A, B and C is in the ratio 2:3:5. A alone can complete the work in 40 days. They all worked together for 5 days and then C left the work. In how many days can A and B together complete the remaining work?

  1. 12 days
  2. 10 days
  3. 8 days
  4. 6 days

Answer: 6 days

Since A:B:C = 2:3:5 and A alone finishes in 40 days, A's rate is 1/40 work/day, so 2 parts = 1/40 and 1 part = 1/80. Thus B's rate = 3/80 and C's rate = 5/80. Together they work at 2/80 + 3/80 + 5/80 = 10/80 = 1/8 per day, so in 5 days they complete 5/8 of the work; remaining work = 3/8. A and B together work at 1/40 + 3/80 = 1/16 per day, so time needed = (3/8) ÷ (1/16) = 6 days.

Q36. A, B, and C together can complete a task in 6 days. If A alone takes 12 days and B alone takes 18 days, how long will C alone take?

  1. 19 days
  2. 30 days
  3. 12 days
  4. 36 days

Answer: 36 days

Their combined rate is \(1/6\) work per day. A's rate is \(1/12\) and B's rate is \(1/18\), so C's rate is \(1/6-1/12-1/18=1/36\). Hence C alone takes 36 days.

Q37. A contractor hires 10 workers who can complete a task in 16 days. After 4 days, he fires 2 workers. How many more days will the remaining workers take to complete the task?

  1. 13 days
  2. 14 days
  3. 15 days
  4. 16 days

Answer: 15 days

Total work = \(10\times16=160\) worker-days. In 4 days, 10 workers do \(10\times4=40\) worker-days, leaving \(120\) worker-days. After 2 workers are fired, 8 workers remain, so time needed = \(120/8=15\) days.

Q38. Lalit can finish a work in 15 days. Laxman can finish the same work in 25 days. They work together for 5 days. If the rest of the work is finished by Lalit and Deven in 4 days, then in how many days can Deven alone finish the work?

  1. 30 days
  2. 25 days
  3. 21 days
  4. 20 days

Answer: 20 days

Lalit’s rate is 1/15 and Laxman’s rate is 1/25, so together they do 8/75 of the work per day. In 5 days they complete 40/75 = 8/15, leaving 7/15. Lalit and Deven finish this in 4 days, so their combined rate is 7/60; subtracting Lalit’s rate 1/15 gives Deven’s rate 1/20, so Deven alone takes 20 days.

Q39. A can complete a task in 30 days, and B can complete the same task in 40 days. They work together for 10 days, and then C joins them and completes the remaining work in 5 days. How long will C alone take to complete the task?

  1. 25 days
  2. 26 days
  3. 40 days
  4. 27 days

Answer: 40 days

A’s rate is $1/30$ per day and B’s rate is $1/40$ per day, so together they do $7/120$ per day. In 10 days, they complete $7/12$ of the work, leaving $5/12$. In the next 5 days, A, B, and C together finish $5/12$, so C’s rate is $1/40$ per day, meaning C alone takes 40 days.

Q40. X can complete a task in 12 days, while Y takes 18 days to finish the same task. If they work together for 3 days, what fraction of the work will still remain?

  1. 1/3
  2. 5/12
  3. 7/12
  4. 9/12

Answer: 7/12

X’s rate is 1/12 per day and Y’s rate is 1/18 per day, so together they do 5/36 of the work per day. In 3 days, they complete 15/36 = 5/12 of the work, so the remaining work is 1 - 5/12 = 7/12.

Q41. Three pumps, A, B, and C, can fill a reservoir. A fills it in 5 hours, B in 7 hours, and C in 10 hours. When all three pumps are opened together, they operate for 1.5 hours before pump C is closed. How much additional time will it take to completely fill the reservoir after that?

  1. 1/2 hours
  2. 43/25 hours
  3. 47/48 hours
  4. 45/41 hours

Answer: 47/48 hours

Together, A, B, and C fill at a rate of 1/5 + 1/7 + 1/10 = 31/70 of the reservoir per hour. In 1.5 hours, they fill 93/140, leaving 47/140. After C is closed, A and B fill at 1/5 + 1/7 = 12/35 per hour, so the remaining time is (47/140) ÷ (12/35) = 47/48 hours.

Q42. X, Y, and Z can complete a project in 20, 40, and 60 days respectively. X works every day, while Y and Z join X every third day. How long will it take to finish the project?

  1. 12 7 2 days
  2. 15 5 6 days
  3. 16 5 6 days
  4. 18 days

Answer: 15 5 6 days

X’s 1-day work = 1/20, Y’s = 1/40, Z’s = 1/60. In 3 days, work done = 1/20 + 1/20 + (1/20+1/40+1/60) = 1/10 + 13/120 = 25/120 = 5/24. So 24/5 = 4.8 such cycles are needed, i.e. 14 full days and 4/5 of the next cycle. The total time comes to 15 5/6 days.

Q43. The ratio of efficiencies of workers A and B is 4:3. If A can finish a task in 18 days, in how many days will B finish the same task alone?

  1. 20 days
  2. 22 days
  3. 24 days
  4. 26 days

Answer: 24 days

Since efficiency ratio A:B = 4:3, their time ratio is 3:4. If A takes 18 days, then B takes \(18 \times \frac{4}{3} = 24\) days.

⚔️ Practice SSC CGL (Prelims) General free + battle 1v1 →