Exams › SSC CGL (Prelims) › General › Time and Work
43 questions with worked solutions.
Answer: 38 2/5 days
Let daily work rates be P, Q, and R. Then \(P+Q=1/16\), \(Q+R=1/24\), and \(R+P=1/32\). Adding gives \(2(P+Q+R)=1/16+1/24+1/32=13/96\), so \(P+Q+R=13/192\). Hence \(P=(P+Q+R)-(Q+R)=13/192-1/24=5/192\), so P alone takes \(192/5=38\frac{2}{5}\) days.
Answer: 8.75 days
X’s rate is $1/14$ per day and Y’s rate is $1/10$ per day. Together with Z, the rate is $1/3.5=2/7$ per day. So Z’s rate is $2/7 - 1/14 - 1/10 = 2/35$, meaning Z alone takes 35/4 = 8.75 days.
Answer: 4 days
P’s rate is $1/6$ per day and Q’s rate is $-1/4$ per day. In 3 days P completes $1/2$ work; in the next 2 days, together they do $2(1/6-1/4)=-1/6$ work, so remaining work is $1/2+1/6=2/3$. P alone needs $(2/3)/(1/6)=4$ days.
Answer: 16 km/h
The distance between the cities is $24 \times 5 = 120$ km. To cover 120 km in 3 hours, the required speed is $120/3 = 40$ km/h. So the increase in speed is $40 - 24 = 16$ km/h.
Answer: 1/3
X's one-day work is $1/10$ and Y's one-day work is $1/15$. Together they do $1/10 + 1/15 = 1/6$ of the work per day, so in 4 days they complete $4/6 = 2/3$ of the work. Therefore, the remaining work is $1 - 2/3 = 1/3$.
Answer: 22 days
Let the daily work rates be X, Y, Z. Then X+Y = 1/14 and Y+Z = 1/18. The total work done is 6X + 8Y + 12Z = 1. Solving these equations gives Z ≈ 1/22 of the work per day, so Z alone takes about 22 days.
Answer: ₹ 3,200
P's rate is $1/15$ and Q's rate is $1/20$, so together they work at $7/60$ per day. In 4 days, P+Q do $28/60=7/15$ of the work, so R does the remaining $8/15$. Therefore R's payment is $6000\times \frac{8}{15}=3200$.
Answer: 9.375 hrs
Since time is inversely proportional to work rate, X:Y time ratio $=5:3$ means X:Y efficiency ratio $=3:5$. If Y takes 15 hours, X takes $15\times \frac{5}{3}=25$ hours. Together their rate is $1/25+1/15=8/75$, so time taken is $75/8=9.375$ hours.
Answer: 12 days
If D takes x days, then C, being four times as efficient, takes x/4 days. Given x - x/4 = 45, so x = 60 and C takes 15 days. Together, their rate is 1/15 + 1/60 = 1/12, so they finish in 12 days.
Answer: 6 days
P’s rate is 1/16 per day and Q’s rate is 1/24 per day, so together they do 5/48 of the work per day. In 6 days they complete 5/8 of the work, leaving 3/8, which P finishes in 6 days.
Answer: 72 days
Let M’s and N’s daily work rates be \(m\) and \(n\). Then \(m+n=1/36\). Also, after M works for 20 days, the remaining work is what N completes in 52 days, so \(1-20m=52n\). Solving these two equations gives \(n=1/72\), so N alone takes 72 days.
Answer: 19 days
P’s 1-day work = \(1/24\), Q’s = \(1/36\), and R’s = \(1/72\). In every 4-day cycle, P works 4 days and gets help from Q and R on the 4th day, so total work per cycle is \(3\cdot\frac{1}{24}+\left(\frac{1}{24}+\frac{1}{36}+\frac{1}{72}\right)=\frac{1}{8}+\frac{1}{12}=\frac{5}{24}\). After 4 such cycles, 20 days, the work would exceed 1, so the exact completion occurs on day 19.
Answer: 6 min
Initially, A fills $1/18$ tank per minute and B fills $1/36$ per minute, so together they fill $1/12$ tank per minute. In 6 minutes they fill $6/12 = 1/2$ tank. After the change, A works at $1/36$ and B at $1/18$, so the combined rate is again $1/12$ tank per minute; thus the remaining half takes 6 more minutes.
Answer: 10 hours
Tap X fills \(\frac{1}{12}\) cistern per hour and Tap Y fills \(\frac{1}{15}\) per hour, while Z empties \(\frac{1}{20}\) per hour. Net rate = \(\frac{1}{12}+\frac{1}{15}-\frac{1}{20}=\frac{1}{10}\) cistern per hour, so the cistern fills in 10 hours.
Answer: 2 min 30 sec
Initially, A fills \(1/10\) tank/min and B fills \(1/15\) tank/min, so together they fill \(1/6\) tank/min. In 3 minutes, they fill \(1/2\) tank. After that, A’s rate becomes \(\frac{1}{3}\cdot\frac{1}{10}=\frac{1}{30}\) and B’s rate becomes \(2.5\cdot\frac{1}{15}=\frac{1}{6}\), so combined rate is \(\frac{1}{5}\) tank/min. Remaining half tank takes \(\frac{1/2}{1/5}=2.5\) minutes = 2 min 30 sec.
Answer: ₹ 576
Let P's efficiency be 1 unit and Q's efficiency be 1.5 units. P does 20% of the work alone, and the remaining 80% is done together in the ratio 1 : 1.5 = 2 : 3. So Q's share of the total work is \(\frac{3}{5}\times 80\% = 48\%\), hence Q earns \(48\%\) of ₹1200 = ₹576.
Answer: ₹432
Let A's efficiency be 1 and B's be 1.5. If the total job is 1 unit, A does all of it, while B does only the last 60%, so B's work contribution is $1.5\times 0.6=0.9$ units and A's is 1 unit. Thus the ratio A:B is $1:0.9=10:9$, so B's share is $1200\times\frac{9}{19}=₹432$.
Answer: 40 min
The boy's rate is \(5/4\) L/min and the girl's rate is \(4/5\) L/min. Their combined rate is \(5/4+4/5=41/20\) L/min. Time to fill 82 liters is \(82\div(41/20)=40\) minutes.
Q19. If 4 workers take 4 days to build 4 walls, how long will 50 workers take to build 50 walls?
Answer: 4 days
If 4 workers build 4 walls in 4 days, then 1 worker builds 1 wall in 4 days. Therefore, 50 workers will build 50 walls in the same 4 days.
Answer: 40%
P’s one-day work = \(1/5\), Q’s one-day work = \(1/10\). Together they do \(1/5 + 1/10 = 3/10\) of the work per day, so in 2 days they complete \(6/10 = 60\%\). Hence, 40% work is left.
Answer: 5:2
15 women finish the work in 20 days, so 1 woman's 1-day work is 1/(15×20). Similarly, 12 men finish it in 10 days, so 1 man's 1-day work is 1/(12×10). The ratio of efficiency of a man to a woman is therefore [1/120] : [1/300] = 300:120 = 5:2.
Answer: 60%
If Y's efficiency is 2 units, then X's efficiency is 3 units because X is 50% more efficient. So together they work in the ratio 3:2, and X's share of the work is 3/(3+2) = 3/5 = 60%.
Answer: 20 Days
Since 4 men alone finish in 40 days, their rate is \(1/40\) task per day. Similarly, 6 women alone also have rate \(1/40\) per day, so together their rate is \(1/20\) task per day, meaning 20 days.
Q24. 40 men can do a piece of work in 10 days. Find the time required by 25 men to do double the work.
Answer: 32 Days
40 men working for 10 days complete one job, so total work = 400 man-days. Double the work = 800 man-days. With 25 men, time required = \(800/25 = 32\) days.
Answer: 30 days
Let the daily work rates of A, B, and C be a, b, and c. Given a = b + c, a + b = 1/12, and c = 1/60. Substituting a = b + c gives 2b + c = 1/12, so 2b + 1/60 = 1/12, which yields b = 1/30.
Answer: 25%
Total work = 25 × 40 = 1000 worker-days. Work done by 50 workers in 5 days = 50 × 5 = 250 worker-days. So the fraction completed is 250/1000 = 1/4 = 25%.
Q27. If 12 men can build a wall in 15 days, in how many days can 18 men complete the same work?
Answer: 10
Total work = 12 × 15 = 180 man-days. If 18 men work on it, days required = 180/18 = 10 days. So the correct answer is 10.
Answer: 51 days
If 10 men finish the work in 170 days, then 1 man’s 1-day work is \(\frac{1}{10\times170}\). Similarly, 1 woman’s 1-day work is \(\frac{1}{15\times170}\). Adding the rates of 20 men and 20 women gives the total daily work, from which the time comes out to 51 days.
Answer: 12 min
The two taps fill at rates of \(1/6\) and \(1/4\) tub per minute, while the pipe empties at \(1/3\) tub per minute. Net rate = \(1/6 + 1/4 - 1/3 = 1/12\) tub per minute. So the tub will be full in 12 minutes.
Answer: 10 hours
Sudarshan’s rate is 50/10 = 5 pages per hour. Together they copy 300/40 = 7.5 pages per hour, so Prakash’s rate is 2.5 pages per hour. To copy 25 pages, Prakash needs 25/2.5 = 10 hours.
Q31. The time taken to cover 132 km by car is 1 hour. Find the time taken to cover 88 km by car.
Answer: 40 min
If 132 km takes 1 hour, then speed is 132 km/h. Time for 88 km is $88/132 = 2/3$ hour, which is 40 minutes.
Answer: 8.5 days
A’s rate is \(1/15\) work/day and B’s rate is \(1/20\) work/day. Together, their rate is \(1/15+1/20=7/60\) work/day, so time taken is \(60/7\approx 8.57\) days.
Answer: 36 km
The difference in times is 36 minutes = 0.6 hour. For the same distance \(d\), the time difference is \(\frac{d}{10}-\frac{d}{12}\). Solving gives \(d\left(\frac{1}{60}\right)=0.6\), so \(d=36\) km.
Answer: 10 h
The distance covered is 50 × 8 = 400 km. At 40 km/h, time taken = 400/40 = 10 hours. So the correct answer is 10 h.
Answer: 6 days
Since A:B:C = 2:3:5 and A alone finishes in 40 days, A's rate is 1/40 work/day, so 2 parts = 1/40 and 1 part = 1/80. Thus B's rate = 3/80 and C's rate = 5/80. Together they work at 2/80 + 3/80 + 5/80 = 10/80 = 1/8 per day, so in 5 days they complete 5/8 of the work; remaining work = 3/8. A and B together work at 1/40 + 3/80 = 1/16 per day, so time needed = (3/8) ÷ (1/16) = 6 days.
Answer: 36 days
Their combined rate is \(1/6\) work per day. A's rate is \(1/12\) and B's rate is \(1/18\), so C's rate is \(1/6-1/12-1/18=1/36\). Hence C alone takes 36 days.
Answer: 15 days
Total work = \(10\times16=160\) worker-days. In 4 days, 10 workers do \(10\times4=40\) worker-days, leaving \(120\) worker-days. After 2 workers are fired, 8 workers remain, so time needed = \(120/8=15\) days.
Answer: 20 days
Lalit’s rate is 1/15 and Laxman’s rate is 1/25, so together they do 8/75 of the work per day. In 5 days they complete 40/75 = 8/15, leaving 7/15. Lalit and Deven finish this in 4 days, so their combined rate is 7/60; subtracting Lalit’s rate 1/15 gives Deven’s rate 1/20, so Deven alone takes 20 days.
Answer: 40 days
A’s rate is $1/30$ per day and B’s rate is $1/40$ per day, so together they do $7/120$ per day. In 10 days, they complete $7/12$ of the work, leaving $5/12$. In the next 5 days, A, B, and C together finish $5/12$, so C’s rate is $1/40$ per day, meaning C alone takes 40 days.
Answer: 7/12
X’s rate is 1/12 per day and Y’s rate is 1/18 per day, so together they do 5/36 of the work per day. In 3 days, they complete 15/36 = 5/12 of the work, so the remaining work is 1 - 5/12 = 7/12.
Answer: 47/48 hours
Together, A, B, and C fill at a rate of 1/5 + 1/7 + 1/10 = 31/70 of the reservoir per hour. In 1.5 hours, they fill 93/140, leaving 47/140. After C is closed, A and B fill at 1/5 + 1/7 = 12/35 per hour, so the remaining time is (47/140) ÷ (12/35) = 47/48 hours.
Answer: 15 5 6 days
X’s 1-day work = 1/20, Y’s = 1/40, Z’s = 1/60. In 3 days, work done = 1/20 + 1/20 + (1/20+1/40+1/60) = 1/10 + 13/120 = 25/120 = 5/24. So 24/5 = 4.8 such cycles are needed, i.e. 14 full days and 4/5 of the next cycle. The total time comes to 15 5/6 days.
Answer: 24 days
Since efficiency ratio A:B = 4:3, their time ratio is 3:4. If A takes 18 days, then B takes \(18 \times \frac{4}{3} = 24\) days.