Exams › SSC CGL (Prelims) › General
Correct answer: 6 days
Since A:B:C = 2:3:5 and A alone finishes in 40 days, A's rate is 1/40 work/day, so 2 parts = 1/40 and 1 part = 1/80. Thus B's rate = 3/80 and C's rate = 5/80. Together they work at 2/80 + 3/80 + 5/80 = 10/80 = 1/8 per day, so in 5 days they complete 5/8 of the work; remaining work = 3/8. A and B together work at 1/40 + 3/80 = 1/16 per day, so time needed = (3/8) ÷ (1/16) = 6 days.