A can complete a task in 15 days, and B can complete the same task in 20 days. How long will it take them to complete the task together?
- 5.5 days
- 6.5 days
- 7.5 days
- 8.5 days
Correct answer: 8.5 days
Solution
A’s rate is \(1/15\) work/day and B’s rate is \(1/20\) work/day. Together, their rate is \(1/15+1/20=7/60\) work/day, so time taken is \(60/7\approx 8.57\) days.