Exams › SSC CGL (Prelims) › General
P completes a job in 15 days and Q in 20 days. P and Q agree to do the work for ₹6,000. With R, they finish in 4 days. What is R's payment?
- ₹ 1,800
- ₹ 3,200
- ₹ 2,400
- ₹ 2,800
Correct answer: ₹ 3,200
Solution
P's rate is $1/15$ and Q's rate is $1/20$, so together they work at $7/60$ per day. In 4 days, P+Q do $28/60=7/15$ of the work, so R does the remaining $8/15$. Therefore R's payment is $6000\times \frac{8}{15}=3200$.