C is four times as efficient a worker as D, and C can complete a work in 45 days less than D. If they work together, in how many days can they finish the work?
- 10 days
- 12 days
- 15 days
- 18 days
Correct answer: 12 days
Solution
If D takes x days, then C, being four times as efficient, takes x/4 days. Given x - x/4 = 45, so x = 60 and C takes 15 days. Together, their rate is 1/15 + 1/60 = 1/12, so they finish in 12 days.