StreakPeaked· Practice

ExamsSSC CGL (Prelims)General

P can do a piece of work in 5 days, and Q can do it in 10 days. If they work together for 2 days, how much of the work will be left?

  1. 20%
  2. 30%
  3. 40%
  4. 50%

Correct answer: 40%

Solution

P’s one-day work = \(1/5\), Q’s one-day work = \(1/10\). Together they do \(1/5 + 1/10 = 3/10\) of the work per day, so in 2 days they complete \(6/10 = 60\%\). Hence, 40% work is left.