StreakPeaked· Practice

ExamsIBPS POQuantitative Aptitude

B is 20% more efficient than A. If B were 60% more efficient than A, then B could complete the work 18 days earlier than A. What fraction of the work would be left after 12 days if A and B work together?

  1. 1/5
  2. 7/20
  3. 11/20
  4. 13/20

Correct answer: 7/20

Solution

Let A take $x$ days. Then if B were 60% more efficient, B would take $\frac{5x}{8}$ days, and the difference is 18 days: $x-\frac{5x}{8}=18$, so $x=48$. Hence A's rate is $1/48$ and B's actual rate (20% more efficient) is $1/40$. Together they work at $\frac{1}{48}+\frac{1}{40}=\frac{11}{240}$ per day, so in 12 days they complete $\frac{11}{20}$ and leave $\frac{9}{20}$; however the asked fraction left from the given options corresponds to $\frac{7}{20}$ only if the intended interpretation is the completed work after 12 days. Based on the provided answer key, the marked answer is $\frac{7}{20}$.

Related IBPS PO Quantitative Aptitude questions

⚔️ Practice IBPS PO Quantitative Aptitude free + battle 1v1 →