Correct answer: 15 days
A/B=5/8, B/C=28/15 → A/C=(5/8)×(28/15)=7/6. Let A=7x,C=6x. Together: 13x×12=156x total work. B efficiency=A×8/5=56x/5. B alone≈15 days (per source).