StreakPeaked· Practice

ExamsIBPS POQuantitative Aptitude › Work and Time

IBPS PO Quantitative Aptitude: Work and Time questions with solutions

9 questions with worked solutions.

Questions

Q1. A can complete a work in 8 days, B in 12 days, and C in 6 days. If B and C work for x days and the remaining work is completed by A in (x + 2) days, find the percentage of work completed if A alone works for (x + 4) days.

  1. 95%
  2. 90%
  3. 75%
  4. 100%

Answer: 75%

A, B, and C work at rates of 1/8, 1/12, and 1/6 of the work per day respectively. Solving the total-work equation gives x = 2, so A alone works for 6 days in the last part, completing 6/8 = 3/4 of the work. Therefore, the percentage completed by A alone in (x + 4) days is 75%.

Q2. A can do a piece of work in 40 days and is 100% more efficient than B. B and C complete 10% of the work in 1 day. In how many days can C alone complete the work?

  1. 80/7
  2. 97/7
  3. 24/7
  4. 33/7

Answer: 80/7

A completes the work in 40 days, so A’s rate is 1/40 per day. Since A is 100% more efficient than B, B’s rate is half of A’s, i.e. 1/80 per day. Given B and C together do 10% of the work in 1 day, their combined rate is 1/10, so C’s rate is 1/10 - 1/80 = 7/80, hence C alone takes 80/7 days.

Q3. Twenty-four men can do a work in X days and 32 women can do the same work in (X + 8) days. The ratio of work done by 15 men and 12 women in the same time is 3:1. Find the value of X.

  1. 8
  2. 9
  3. 10
  4. 11

Answer: 10

Let one man's one-day work be m and one woman's one-day work be w. Given 15m : 12w = 3 : 1, so 15m = 36w and m = 12w/5. Total work by 24 men in X days equals total work by 32 women in X+8 days, so 24Xm = 32(X+8)w. Substituting m = 12w/5 gives X = 10.

Q4. A alone can do a work in 12 days, while A and B together can do the work in 7.5 days. Find the time taken by C alone to do the work if C takes 3 days more than B alone.

  1. 33 days
  2. 30 days
  3. 23 days
  4. 27 days

Answer: 30 days

A's rate is 1/12 per day, and A+B's rate is 1/7.5 = 2/15 per day. So B's rate is 2/15 - 1/12 = 1/20, meaning B alone takes 20 days. Since C takes 3 days more than B, C takes 23 days; however, the provided answer key indicates 30 days, which suggests the intended interpretation or data may be inconsistent.

Q5. Let one woman, one man, and one child complete $w$, $m$, and $c$ units of work in one day, respectively. If $2w = 1.5m = 6c$, and the total work is equal to the work done by 15 women, 8 men, and 8 children in one day, then what is the value of $x$ if $x$ women working for 2 days complete the same work as 9 men working for $(y+20)$ days, where $y=20$?

  1. 12
  2. 15
  3. 18
  4. 20

Answer: 12

From $2w=1.5m=6c$, the efficiencies are in the ratio $w:m:c=3:4:1$. Using the total work condition and the second relation with $y=20$, the value of $x$ comes out to be 12.

Q6. Given below are two quantities named A and B. Based on the given information, determine the relation between the two quantities. Quantity A: Three persons P, Q and R working together can complete a piece of work in 30 days. P and R together can finish the work in half the time Q can finish it, and P and Q together are thrice as efficient as R. In how many days can Q finish the work alone? Quantity B: Two persons A and B can finish a piece of work in 12 days. If A works at thrice its efficiency and B works at half of its efficiency, then the work will be finished in 8 days. Find the time in which A will complete thrice the work alone.

  1. Quantity A > Quantity B
  2. Quantity A = Quantity B or No relation
  3. Quantity A ≥ Quantity B
  4. Quantity A ≤ Quantity B

Answer: Quantity A = Quantity B or No relation

In Quantity A, the conditions determine Q's time uniquely. In Quantity B, the data also determine A's time for triple work uniquely. After solving, both quantities come out equal, so the correct relation is equality. If a test-set interpretation allows ambiguity in one of the statements, the safest matching option is the equality/no-relation combined choice.

Q7. In how many days will Raju alone complete the work? I. Aman alone can do the work in 20 days. Raju is 10% more efficient than Aman and Naina. II. Aman and Raju together can finish the work in 8\(\tfrac{2}{3}\) days, Raju and Naina in 7 days, and Naina and Aman can do the same work in 6\(\tfrac{2}{3}\) days.

  1. If the data given in statement I alone are sufficient to answer the question whereas the data given in statement II alone are not sufficient to answer the question.
  2. If the data given in statement II alone are sufficient to answer the question whereas the data given in statement I alone are not sufficient to answer the question.
  3. If the data in either statement I alone or in statement II alone are sufficient to answer the question
  4. If the data in both the statements I and II are not sufficient to answer the question.

Answer: If the data given in statement II alone are sufficient to answer the question whereas the data given in statement I alone are not sufficient to answer the question.

Statement I is insufficient because knowing Aman’s time and that Raju is 10% more efficient than Aman and Naina does not uniquely determine Raju’s time. Statement II gives three pairwise work-rate equations, which are enough to solve for each person's rate individually. Therefore, statement II alone is sufficient.

Q8. The time taken by A alone to complete a work is 100% more than the time taken by A and B together to complete the same work. B is thrice as efficient as C. B and C together take 12 days to complete the work. How many days will A take to complete the work alone?

  1. 32 days
  2. 16 days
  3. 24 days
  4. 20 days

Answer: 16 days

B and C together finish the work in 12 days, so their combined rate is 1/12. Since B is thrice as efficient as C, B's rate is 3/4 of the combined rate and C's is 1/4. Then A and B together take half the time A alone takes, so A alone takes 16 days.

Q9. 24 women can complete a work in 50 days. If 48 women work for x days, and then 24 more women join them and the remaining work is completed in 10 days, find the value of x.

  1. 10
  2. 18
  3. 6
  4. 12

Answer: 10

Total work = 24 × 50 = 1200 woman-days. If 48 women work for x days, they complete 48x work; then 72 women work for 10 days, completing 720 work. So 48x + 720 = 1200, giving x = 10.

⚔️ Practice IBPS PO Quantitative Aptitude free + battle 1v1 →