10 men can do \(\tfrac{2}{5}\) of a work in 10 days. Find the time taken by 25 men to complete the whole work.

  1. 10 days
  2. 20 days
  3. 15 days
  4. 8 days

Correct answer: 10 days

Solution

If 10 men do \(\tfrac{2}{5}\) of the work in 10 days, then 100 men-days correspond to \(\tfrac{2}{5}\) work. So the full work needs \(100\times \tfrac{5}{2}=250\) men-days. With 25 men, time = \(250/25 = 10\) days.