A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working together and A quits 10 days before the project is completed, in how many days will the project be completed?

  1. 18 days
  2. 27 days
  3. 26.67 days
  4. 16 days

Correct answer: 18 days

Solution

A’s rate is \(1/20\) and B’s rate is \(1/30\), so together they work at \(1/12\) per day. If the project takes \(T\) days, then A works for \(T-10\) days and B for \(T\) days, giving \((T-10)/20 + T/30 = 1\). Solving gives \(T = 18\) days.