A can complete a work in 15 days and B in 18 days. A works for 5 days, then B completes the rest. How many days does B take to complete the remaining work?

  1. 10 days
  2. 12 days
  3. 15 days
  4. 18 days

Correct answer: 12 days

Solution

A's 1-day work is \(1/15\), so in 5 days A completes \(5/15 = 1/3\) of the work. Remaining work is \(2/3\), and B's rate is \(1/18\) per day, so time taken by B is \((2/3) \div (1/18) = 12\) days.