15 men can do a work in X days. 20 women can do the same work in 2X days. 57 women can do the work in 20 days. In how many days can 9 men do the same work?

  1. 47.5 days
  2. 42.5 days
  3. 52.5 days
  4. 45 days

Correct answer: 47.5 days

Solution

Let total work be W. From 57 women finishing in 20 days, one woman’s daily work rate is W/1140. Using 20 women in 2X days, we get 20 × 2X × (W/1140) = W, so X = 28.5. Then 15 men finish W in 28.5 days, so 9 men will take 47.5 days.