A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

  1. Rs. 375
  2. Rs. 400
  3. Rs. 600
  4. Rs. 800

Correct answer: Rs. 400

Solution

A and B together do $\frac{1}{6}+\frac{1}{8}=\frac{7}{24}$ of the work per day, so in 3 days they do $\frac{7}{8}$. Thus C does the remaining $\frac{1}{8}$ of the work. C's payment is therefore $\frac{1}{8}\times 3200=400$.