In a PERT chart, the activity time distribution is

  1. Normal
  2. Binomial
  3. Poisson
  4. Beta

Correct answer: Normal

Solution

In classical PERT, activity durations are modeled using a beta distribution because it is flexible and bounded by optimistic and pessimistic estimates. The expected time is then computed from these estimates. So the correct distribution is beta, not normal.