Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is ________ hours. Part | Milling (hours) | Polishing (hours) P1 | 8 | 6 P2 | 3 | 2 P3 | 3 | 4 P4 | 4 | 6 P5 | 5 | 7 P6 | 6 | 4 P7 | 2 | 1

  1. 31
  2. 33
  3. 30
  4. 32

Correct answer: 33

Solution

By Johnson's two-machine rule the optimal sequence is P3,P4,P5,P1,P6,P2,P7. Computing milling completion then polishing completion gives a total makespan of 33 hours, not 32.