Exams › GATE › Technical
The net requirements of an item over 5 consecutive weeks are 50, 0, 15, 20, 20. The inventory carrying cost is Re. 1 per item per week and the ordering cost is Rs. 100 per order. Starting inventory is zero. Using the Least Unit Cost Technique, the cost of the plan (in Rs.) is
- 200
- 250
- 255
- 260
Correct answer: 250
Solution
In the Least Unit Cost technique, we test how many weeks of demand should be covered by the first order and compute total cost per unit for each feasible coverage. The minimum average cost occurs for the plan whose total cost is Rs. 250. Hence, the cost of the plan is 250.
Related GATE Technical questions
- The time-series forecasting method that gives equal weightage to each of the \(m\) most recent observations is
- In a linear programming problem, if a resource is not fully utilized, the shadow price of that resource is
- A factory produces \(m\) products \((i=1,2,\dots,m)\), each of which requires processing on \(n\) workstations \((j=1,2,\dots,n)\). Let \(a_{ij}\) be the processing time that one unit of the \(i^{\text{th}}\) product requires on the \(j^{\text{th}}\) workstation. Let the revenue from selling one unit of the \(i^{\text{th}}\) product be \(r_i\), and let \(h_i\) be the holding cost per unit per time period for the \(i^{\text{th}}\) product. The planning horizon consists of \(T\) time periods \((t=1,2,\dots,T)\). The minimum demand that must be satisfied in time period \(t\) is \(d_{it}\), and the capacity of the \(j^{\text{th}}\) workstation in time period \(t\) is \(c_{jt}\). Consider the aggregate planning formulation below, with decision variables \(S_{it}\) (amount of product \(i\) sold in time period \(t\)), \(X_{it}\) (amount of product \(i\) manufactured in time period \(t\)), and \(I_{it}\) (amount of product \(i\) held in inventory at the end of time period \(t\)). \[ \max \sum_{t=1}^{T}\sum_{i=1}^{m}(r_iS_{it}-h_iI_{it}) \] subject to \[ S_{it}\ge d_{it}\quad \forall i,t \] The capacity constraints and inventory balance constraints for this formulation are
- The demand and forecast of an item for five months are given in the table. Month | Demand | Forecast April | 225 | 200 May | 220 | 240
- Parts P1–P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both operations for all 7 parts is ________ hours. Part | Milling (hours) | Polishing (hours) P1 | 8 | 6 P2 | 3 | 2 P3 | 3 | 4 P4 | 4 | 6 P5 | 5 | 7 P6 | 6 | 4 P7 | 2 | 1
- The expected time \(t_e\) of a PERT activity in terms of optimistic time \(t_o\), pessimistic time \(t_p\), and most likely time \(t_l\) is given by
⚔️ Practice GATE Technical free + battle 1v1 →