If 12 men can complete a work in 8 days, how many days will 16 men take?

  1. 6
  2. 5
  3. 4
  4. 7

Correct answer: 6

Solution

The total work is constant, so men × days = constant. Here, 12 × 8 = 96 man-days. With 16 men, days = 96 ÷ 16 = 6.