A, B and C together can complete 66.67% of work in X days. Find how many days A alone takes.
- 15 days
- 18 days
- 20 days
- 24 days
Correct answer: 20 days
Solution
From the given conditions about A, B, C's combined completion of 2/3 of the work and other individual rate information, A's individual time is 20 days.