Exams › GATE › Technical
The total number of decision variables in the objective function of an assignment problem of size n × n (n jobs and n machines) is
- n²
- 2n
- 2n − 1
- n
Correct answer: n²
Solution
In an assignment problem of size n × n, each job can be assigned to each machine, resulting in n jobs having n possible assignments each, which totals to n² decision variables.