A component can be produced by any of the four processes I, II, III and IV. The fixed cost and the variable cost for each of the processes are listed below. Process | Fixed cost (in Rs.) | Variable cost per piece (in Rs.) I | 20 | 3 II | 50 | 1 III | 40 | 2 IV | 10 | 4 The most economical process for producing a batch of 100 pieces is

  1. I
  2. II
  3. III
  4. IV

Correct answer: II

Solution

Process II is the most economical choice because it has the lowest total cost when considering both fixed and variable costs for producing 100 pieces, resulting in a total cost of Rs. 150, which is less than the total costs of the other processes.