Consider the following data for a project of 300 days duration. Budgeted Cost of Work Scheduled (BCWS) = Rs. 200 Budgeted Cost of Work Performed (BCWP) = Rs. 150 Actual Cost of Work Performed (ACWP) = Rs. 190 The ‘schedule variance’ for the project is

  1. (−) Rs. 50
  2. (−)50 days
  3. (+) Rs. 50
  4. (+)50 days

Correct answer: (−) Rs. 50

Solution

The schedule variance is calculated by subtracting the Budgeted Cost of Work Scheduled (BCWS) from the Budgeted Cost of Work Performed (BCWP). In this case, BCWP (Rs. 150) minus BCWS (Rs. 200) results in a negative variance of Rs. 50, indicating that the project is behind schedule.