A set of jobs U, V, W, X, Y, Z arrive at time t = 0 to a production line consisting of two work stations in series. Each job must be processed by both work stations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below. Job: U V W X Y Z Workstation 1: 5 7 3 4 6 8 Workstation 2: 4 6 6 8 5 7 The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is

  1. W-X-Z-V-Y-U
  2. W-X-V-Z-Y-U
  3. W-U-Z-V-Y-X
  4. U-Y-V-Z-X-W

Correct answer: W-X-Z-V-Y-U

Solution

The sequence W-X-Z-V-Y-U minimizes the makespan by prioritizing jobs with shorter processing times on the first workstation, allowing for a more efficient flow through both workstations and reducing idle time.